Submittals: List, Schedule, and Requirements

Submittal List and Schedule

  • The general contractor shall prepare a detailed list and schedule of all submittal items to be sent to the structural engineer prior to the start of construction.

  • This list shall be updated and revised as the project progresses.


Submittal Requirements

  • Review:

    • All submittals must be reviewed and electronically stamped by the general contractor before submission to the design team (No Exceptions).
  • Transmittal Sheet:
    Each submittal must include a transmittal sheet containing:

    1. Submittal Number Format example: 03 30 00-01.00 (Division, Submittal # for Division, Issue #; e.g., first submittal, first issue of a concrete submittal)
    2. Brief Description of submittal contents
    3. Date Issued
    4. Requested Return Date
    5. Issuing Party Name, phone number, and email
  • Format:

    • Submittals must be provided in electronic PDF format.
    • Scanned copies of printed documents are not acceptable.
  • Completeness:

    • Omission of any materials from shop drawings does not relieve the contractor of the responsibility to furnish and install all required materials, whether shown or commented in the shop drawings.
  • Review Time:

    • Allow a minimum of 14 days for structural review of all submittals.
    • Expedited review may be requested for an agreed-upon fee with the structural engineer.
  • Structural Steel Submittals:

    • Must include the SDS/2 or Tekla model, which will serve as a visual aid to the shop drawings.

Reference

  • Refer to the project specifications for a complete list of required submittals.

Engineer Review Stamp Designations

All designations indicate review for general conformance with construction documents:

Designation Meaning
No Exceptions No items conflict with the construction documents; no resubmittal required.
Exceptions Noted Items conflict with construction documents; revisions needed before "For Construction" submittal.
Revise and Resubmit Significant conflicts with construction documents; resubmittal required "For Review".
Not Reviewed Submittal is not structural.
For Information Only Submittal does not require review; filed for record.
Impact to Structure Reviewed only for structural impact.