## xxx

Proposal for OpeningDesign's Architecture & Engineering Services


Thank you for the opportunity to submit our proposal for the lobby renovation of -------- We are excited about the project and the potential of working together.

Although a more nuanced list of requirements will undoubtedly unfold as the project evolves, on a high-level, we understand that the project will include the following...

  • Incorporate a new elevator that spans the 3 floors in and around the existing lobby area.
    • Priority given to locating elevator in an area to increase or maximize rentable square footage
  • Newly updated, ADA complaint restrooms on all 3 floors
  • Throughout the 3 floors, newly updated finishes in and around the lobby and public corridors

As we understand it, the following will not be included in this proposal scope.

  • Inside the tenant suites, other than the adjoining walls (potentially) near the newly renovated elevator/lobby/restroom areas.
  • Any exterior work

Phases & Scope of Services

  • Phase 1 - Programming (approximate duration/fee: 0.5 weeks / 5% )

    • Perform field measurements/drawings of existing conditions to compose as-built drawings
    • Conduct building code analysis & summary
  • Phase 2 - Schematic Design (approximate duration/fee: 1 weeks / 10% )

    • At the beginning of this phase, we will take the agreed-on list of requirements and provide a maximum of (2) design options. These design options will address varying approaches in the following criteria.
      • Functional relationship of the various spaces
      • Structural considerations
      • Mechanical considerations
      • Plumbing Considerations
      • Major equipment locations
      • Code restrictions/requirements
  • Concepts will be presented in the following formats * 3-dimensional Renderings/Sketches * Floor Plans * Elevations * Sections

    • Continue researching applicable building code
    • If necessary, start coordinating and eliciting feedback from the various engineering disciplines
  • Phase 3 - Design Development (approximate duration/fee: 2 weeks / 25% )

    • Upon approval of schematic design/project budget, we will further develop and refine the design documentation
    • Developed deliverables will include:
      • Floor Plans
      • Site Plan
      • Elevations
      • Sections
      • Select details
    • Propose, select, and refine materials and finish options
    • Continue to coordinate drawings with the various subs/engineering disciplines
  • Phase 4 - Construction Documents (approximate duration/fee: 3 weeks / 35% )

    • Will complete the following drawings for permit and construction:
      • Architectural
        • Demolitions Plans
        • Floor Plans
        • Reflected Ceiling Plans
          • Lighting Layout
        • Interior Elevations
          • Including Millwork/Casework
        • Details
        • Door/Window/Finish Schedules
      • Structural Plans
      • Construction Specifications as necessary
    • Continue to coordinate and communicate with various engineering consultants, if necessary.
  • Phase 5 - Bidding and Construction Contract Negotiation (approximate duration/fee: 0.5 weeks / 5% )

    • Submit/manage any municipal plan reviews and/or permits.
    • Answer contractor's bid questions, issue clarifications.
  • Phase 6 - Construction Administration (approximate duration/fee: NA / 20% )

    • Weekly site visits, assuming a typical construction pace.
    • Respond to RFIs (request for information)
    • Review shop drawings and submittals
    • Review substitutions
    • Review change orders
    • Develop punch list
    • If applicable, review application for payments

Fee & Workflow Proposal

Over the years, OpeningDesign has developed a preferred and unique way of working. Although our website's about page provides more detail, in a nutshell, most of our projects are open source and are conducted out-in-the-open.

Simply put, this way of working allows us to be more efficient, ultimately keeping costs down and bringing more value to our clients. Having said that, we understand some clients, for whatever reason, may have hesitations regarding this approach.

To address _____s potential concerns, if any, we would like to offer the following (3) workflow and fee options:

  • Approach (A): A Fully Open Approach where the construction documentation, location, and the names of the parties involved in this contract are known and are shared publicly. All newly created digital documentation/content is open source, that is, will be freely available to any party for future use, assuming the terms such as Attribution and ShareAlike are honored.
  • Approach (B): An Anonymous Open Approach where all newly created documentation is shared publicly, however, the location and the names of the parties involved are kept anonymous. Again, similar to approach (A), all newly created digital documentation/content is open source.
  • Approach (C): The Traditional Approach where all documentation and parties involved remain confidential and private.
  • Please note, no matter which approach (A, B, or C) is used above...
    • Any documentation from parties outside this contract, and/or shared with OpeningDesign prior to the signing of this contract, WILL NOT be shared publicly.
    • Any prior emails, or any emails between MCRED, OpeningDesign, or any other parties during the duration of the project, WILL NOT be shared publicly.
    • Also, we will not make public anything that MCRED explicitly indicates should be kept private.



Not-to-Exceed Fee Proposal Options (A, B, or C):

- Approach (A) Approach (B) Approach (C)
Total Not-to-exceed Fee
(X% of construction costs)
9% 10.5% 12%
Rough estimate of construction
costs of $150,000
$13,500 $15,750 $18,000

*Please note, these are not lump sum fees, but are instead, not-to-exceed fees. If the project costs go down/up, or less/more scope is involved over time, these fee ceilings will adjust relatively.

The Hourly Rates, called out below, will apply until this not-to-exceed fee is reached.


Hourly Rates


- Approach (A) Approach (B) Approach (C) A Rough
Estimated
Percentage
of Fees
Architecture
OpeningDesign
Level 1 $70/HR $80/HR $100/HR 70%
Level 2 $55/HR $65/HR $75/HR 26%
Structural Engineer Consultant
Ntrive
Level 1 $170/HR $170/HR $170/HR 1%
Level 3 $125/HR $125/HR $125/HR 1%
Level 4 $100/HR $100/HR $100/HR 1%
Level 6 $85/HR $85/HR $85/HR 1%
TOTAL 100%

Additionally, the following list of consultants may be required during this project. Their associated billing rates would be accounted for in the overall not-to-exceed A/E fee.

  • Specification Writer
  • Door Hardware Consultant
  • Lighting Consultant
  • Elevator Consultant

Consultant expenses will include an additional 10% to cover in-house administration, handling, financing, and insurance costs.


The Determination of the Not-to-Exceed Fee

For _____s reference and peace of mind, please review the following document as to what the standard practices are for establishing design fees in the construction/architecture industry.

A Guide to Determining Appropriate Fees for the Services of an Architect Consultants.

In referencing page 11, under the following list of assumptions, they suggest an average range for design services to be around 8.3% of construction costs.

  • Building Category = 3
    • (3.6 Commercial or Administrative Office Building from Page 30)
  • Complexity Level = Average
  • Construction Costs = < $5M
  • WITHOUT Basic Engineering Fees

Additionally, per section 1.2 (Fee Adjustment Factors / Variables affecting the Architects Fee) they suggest adjusting the fee based on a list of unique factors (page 13). Of those listed there, the following Factor 1.2.11 is pertinent to your proposed project.


  • 1.2.11 Fee Adjustment Factor 11 (page 21)
    • Renovation to existing Buildings (versus New Construction)
      • Renovation work is well-known for its unknown conditions. This is the reason that it is recommended that renovations to existing buildings be performed on a time basis. If a percentage-fee is used the fee needs to be adjusted and increased to allow for the unknown work and the subsequent design modifications the Architects will need to make. Some provincial associations recommend an adjustment of an additional two-thirds of the fee or an adjustment factor of 1.65 for renovations

If one applied an adjustment factor of 1.65, as suggested above, the adjusted fee would be 13.7% (1.65 x 8.3%) of construction costs.

As you can see from our proposed not-to-exceed fee and hourly rates outlined above, not to mention our eagerness to work with you, we have decided to provide a more economical rate relative what the industry average suggests.

We are confident that through our unique and open way of working and our strong band of collaborators and consultants, that that we will meet and exceed the industry standard of care.


Reimbursable expenses include:

  • Transportation in connection with the project for travel authorized by the client (transportation, lodging and meals)
  • Communication and shipping costs (long distance charges, courier, postage, dedicated web hosting, etc.)
  • Reproduction costs for plans, sketches, drawings, graphic representations and other documents
  • Renderings, models, prints of computer-generated drawings, mock-ups specifically requested by the client
  • Certification and documentation costs for third party certification such as LEED®
  • Fees, levies, duties or taxes for permits, licences, or approvals from authorities having jurisdiction
  • Additional insurance coverage or limits, including additional professional liability insurance requested by the client in a excess of that normally carried by the architect and the architects consultants
  • Direct expenses from additional consultants not specifically outlined in this proposal

Reimbursable expenses include an additional 10% to cover in-house administration, handling, and financing.


Services not included in Proposal

Although we can provide the following services, we are assuming they will either not be necessary, or will be provided by outside parties.

  • Cost Estimation
  • HVAC/Mechanical Design
  • Plumbing Design
  • Electrical Design
  • Fire Alarm & Life Safety
  • Fire Protection
  • Security
  • Acoustical Engineering Services
  • Furniture, Fixtures & Equipment (FF&E) services
  • Hyper-Realistic Renderings
  • Civil Engineering
  • Geotechnical Engineering
  • Land Surveying
  • Landscape Design
  • Environmental Studies and Reports
  • Legal Survey
  • Signage Design/Layout
  • Closeout Record Documents
  • LEED Design
  • Environmental Studies
  • Commissioning Services
  • Post-occupancy Elevation/Studies
  • Maintenance and Operational Programming
  • Building Maintenance Manuals
  • Post-occupancy Evaluation
  • Extensive decorative finish studies


### Boilerplate
  • OpeningDesign will deliver invoices on a monthly basis based on scope complete, with payment due within 30 days of receipt. Invoices overdue past (60) days will be interpreted as an order to stop work on the project.
  • This proposal is valid for 90 days.

We (OpeningDesign) sincerely appreciate the opportunity to provide you with this proposal and look forward to the potential of a fruitful collaboration in the future.

If we have included a service, with in this proposal, that is not necessary and/or one that is missing altogether, please let us know.

If the terms of this proposal are acceptable please sign in the space offered below.

Finally, please don't hesitate to contact me (Ryan Schultz) should you have any questions or require additional information.


Kind Regards,


Ryan Schultz OpeningDesign

P.S.

Needless to say, we know this open approach is a new and unique way of working and we would be happy to have a face to face meeting to address any further questions/concerns you may have.

Also, if curious, the following links will give you a sense of how we're harnessing this open approach on a Sports Complex project we're working on in Jefferson, WI.

  • For native project files go here.
  • For ongoing project communication between the design team go here.












Authorized by:

  • Signature

  • Title

  • Date


License

Per usual, unless otherwise noted, all content associated with OpeningDesign projects is licensed under an open source, 'copyleft' license: Attribution-ShareAlike 4.0 International (CC BY-SA 4.0). Attribution to be given to the entire team associated with the project. Attribution-ShareAlike 4.0 International